Massachusetts Avenue Bridge Replacement Project

Home > Highlighted Projects > Massachusetts Avenue Bridge Replacement Project
 

What's New

MassDOT is hosting a public meeting on Wednesday, April 25, at 6:00 PM at the Harvard Club (374 Commonwealth Avenue, Boston). At this meeting, the project team will discuss final construction and traffic management plans for Phase 3 when the Massachusetts Avenue bridge over the Commonwealth Avenue bypass roadways is replaced. View the meeting notice for more information.

As part of the project to replace the City of Boston's bridge that carries Massachusetts Avenue over Commonwealth Avenue, Massachusetts Avenue north and southbound will be closed in the vicinity of the bridge between the Commonwealth Avenue surface roadways from 10:00 PM on Thursday, May 10, to 5:00 AM on Tuesday, May 15. The Commonwealth Avenue bypasses under the bridge will also be closed to traffic. The closure is necessary to allow crews to replace the bridge. At the direction of the City of Boston, no parking will be allowed along the detour routes. Local access will be maintained to businesses and residences on Commonwealth Avenue and Massachusetts Avenue. Parking will be maintained on Massachusetts Avenue. View the detours map and the No Parking Flyer for more details. Bicyclists and pedestrians will use the Charlesgate East and Hereford Street crossings. MBTA bus service for Routes 1 and CT1 will also be detoured and may be delayed. View the details about bus stop relocations.

Additionally, MassDOT will close the eastbound and westbound Commonwealth Avenue bypass roadways under the bridge from Saturday, May 5, through Wednesday, May 23. The closures are necessary for the contractor to have access to the bridge substructure to prepare for and complete the full bridge replacement.

MassDOT has implemented alternating single lane closures on Massachusetts Avenue north and southbound in the vicinity of the bridge over Commonwealth Avenue. The lane closures will occur periodically, as needed, on weekdays from 10:00 AM to 2:00 PM, and will continue through August 2018. The closures are necessary for the contractor to install utilities for new street lighting and traffic signals.

View the Project Documents & Meeting Materials section below for detour maps, the public meeting presentation, and a construction animation.

About the Project

The Massachusetts Department of Transportation (MassDOT) is undertaking the Massachusetts Avenue Bridge Replacement Project over Commonwealth Avenue to reconstruct the existing bridges carrying Massachusetts Avenue over Commonwealth Avenue in Back Bay. The contract was awarded to SPS New England, Inc. Accelerated bridge construction techniques will be used to minimize traffic impacts and complete the project as quickly as possible. Coordination with other projects in the area and with the City of Boston is a significant focus.

The project area extends east and westbound on Commonwealth Avenue from Charlesgate East to Hereford Street, and on Massachusetts Avenue between the ramps from Commonwealth Avenue east and westbound.

Anticipated Project & Work Schedule

  • Phase 1 - Completed on September 30, 2017
    • Rehabilitation of the bridge substructure and abutment walls along the Commonwealth Avenue westbound bypass roadway under the bridge
    • Commonwealth Avenue westbound bypass road under Massachusetts Avenue is closed, and all westbound traffic is rerouted to the surface roadway
  • Phase 2 - September 30, 2017 into spring 2018
    • Rehabilitation of the bridge substructure and abutment walls along the Commonwealth Avenue eastbound bypass roadway under the bridge
    • Eastbound traffic traveling on the bypass roadway under Massachusetts Avenue shifted to westbound bypass roadway
    • Installation of utilities for new street lighting and traffic signals
    • Access to Massachusetts Avenue from Commonwealth Avenue eastbound will be maintained. Westbound vehicles and bicyclists will continue to use the surface roadway
  • Phase 3 - May 5 to May 23, 2018
    • Replacement of the Massachusetts Avenue bridge over Commonwealth Avenue
  • Phase 4 - May to September 2018
    • Commonwealth Avenue bypass barrier completion, Massachusetts Avenue sidewalk, barrier, and surface work (new lighting, traffic signals, refurbished fence, new pavement, pavement markings, and bike lanes)

Work will take place during extended daytime hours, six days a week.

The schedule is weather dependent and subject to change without notice.

Project Documents & Meeting Materials

Project Team

Owner: City of Boston

Partner: Massachusetts Department of Transportation

Contractor Team:
SPS New England, Inc. – General Contractor
Regina Villa Associates, Inc. – Public Outreach

Contact Us

For questions, comments or issues, please contact Jim Kersten, MassDOT Legislative Liaison, at 857-368-9041 or email James.A.Kersten@state.ma.us