The Official Website of The Massachusetts Department of Transportation - Highway Division
 
Route 53 Middle St. & Winter St. Intersection
Home > Highlighted Projects > Route 53 Middle St. & Winter St. Intersection
 

Welcome to the community webpage for the Route 53 – Middle Street & Winter Street Intersection in Weymouth. This is a federally funded construction project. MassDOT will use this web page to keep residents and businesses regularly informed with information about the construction phases of the project, including planned lane closures.

The project, managed by MassDOT, consists of the reconstruction of two intersections, Washington St and Middle St and Middle St and Winter St. Work will include full depth pavement, new sidewalks, curbing, plantings, wheel chair ramps, utilities and updated traffic lights and signalization that will improve the movement of vehicular and pedestrian traffic at these intersections.

The project will begin in July 2011. It is expected to take approximately 16-18 months and is projected to be completed in August 2012, which includes a winter moratorium period between December 1, 2011 to March 15, 2012.

July 9, 2012 - July 20, 2012

Curb and sidewalk:

Middle St. SW-side (by the culvert)

Traffic signalization activation:

Intersection of Washington St. /Middle St. /Winter St.

Reconstruction of King Philip Monument:

Washington St. /Middle St., E side

WCR:

Washington St. /Middle St., E side

Curbing and retaining wall:

Middle St. E side (Wal-Mart to Stop/Shop Entrance)

Reconstruction of driveway:

Middle St. E side (at Invernizzi Construction)

Mill/ cold plane roadway:

Entire project

Work Hours

7:00 AM -3:00 PM, Monday to Friday

Anticipated Lane Closures or Detour

None

Anticipated Parking, Pedestrian or Access Impacts:

None

Contact Information

If you have any questions, comments, or would like additional information on the project please E-mail Us or contact Donny Dailey, MassDOT Public Affairs at (617) 973-7638.

You can also visit the project contract page and click on the project manager's mailbox.

Translation Disabled  | Translation Support