Starting in November 2010 through April 2011, MassDOT’s contractor successfully completed a 24/7 rapid replacement of the Craigie Drawbridge as required by United States Coast Guard permit. The drawbridge replacement was broken down into the following phases:
- Contractor installed temporary bridges over the existing bridge (November 2010 – December 2010)
- Contractor demolished the existing bridge and repaired the bridge substructure (December 2010 – January 2011)
- Contractor installed a new pre-fabricated bridge (January 2011 – April 2011)
- Streetscape and landscape work to be completed ( April 2011 – August 2011)
Phase 1 - Contractor installed temporary bridges over the existing bridge.

Phase 2 - Contractor demolished existing drawbridge and made substructure repairs.

Phase 3 - New pre-fabricated drawbridge leafs are installed.

|